T&M Stoppage at Dutton


Timleech

Featured Posts

I emailed David Baldacchino to ask whether it was acceptable to have no up-date since 15th December 2014

on progress with this important breach. He has promised an up-date this week!

 

 

At least you got a reply!

My guess is that they can't give any firm prediction until they have started excavating, to find out how much damage has been done (including probably to the new work).

I believe they were still laying the access track last week. The same access track that was taken up after the breach repair.

 

Tim

Edited by Timleech
Link to comment
Share on other sites

 

 

Update on 20/01/2015: Since the New Year we have built an access into the site which means that we have been able to start the repair project.
In the next couple of weeks we will be exposing the problem area and making sure that we have found all of the areas that need repair, and then starting that.
While there are no certainties at this point we are hopeful of completion by Easter.
We will provide a further update in the first week of February.
Link to comment
Share on other sites

 

 

Update on 20/01/2015: Since the New Year we have built an access into the site which means that we have been able to start the repair project.
In the next couple of weeks we will be exposing the problem area and making sure that we have found all of the areas that need repair, and then starting that.
While there are no certainties at this point we are hopeful of completion by Easter.
We will provide a further update in the first week of February.

There is another thread discussing this stoppage here: http://www.canalworld.net/forums/index.php?showtopic=71990

Link to comment
Share on other sites

 

Update on 20/01/2015: Since the New Year we have built an access into the site which means that we have been able to start the repair project.

In the next couple of weeks we will be exposing the problem area and making sure that we have found all of the areas that need repair, and then starting that.

While there are no certainties at this point we are hopeful of completion by Easter.

We will provide a further update in the first week of February.

 

 

Oh well, at least Easter is early this year.

Link to comment
Share on other sites

Paul C, on 20 Jan 2015 - 5:38 PM, said:

 

QuoteUpdate on 20/01/2015: Since the New Year we have built an access into the site which means that we have been able to start the repair project.

In the next couple of weeks we will be exposing the problem area and making sure that we have found all of the areas that need repair, and then starting that.

While there are no certainties at this point we are hopeful of completion by Easter.

We will provide a further update in the first week of February.

 

 

They said that about Holme Lock last year and it eventually opened in June.

Edited by Alan de Enfield
Link to comment
Share on other sites

There is another thread discussing this stoppage here: http://www.canalworld.net/forums/index.php?showtopic=71990

That link just leads to an error message for me, as does the entry in the View New Content list. Looks like it's not just the T&M with probs tonight... :(

Link to comment
Share on other sites

  • 1 month later...

Latest Update

 

Notice Alert

Trent & Mersey Canal
Starts At: Bridge 211, Dutton Hall Bridge
Ends At: Lock 76
Up Stream Winding Hole: Between Bartington Wharf and Bridge 211
Down Stream Winding Hole: Immediately below Dutton Stop Lock (tunnel side of the lock)

Thursday 27 November 2014 15:00 until further notice

Type: Navigation Closure
Reason: Repair

 

Update on 26/02/2015:

 

The repair works at Dutton are now complete and our contractor is away from the site.

However, because of the other works that are on-going to repair wash walls in the area between Preston Brook Tunnel and Soothill Bridge (200) the canal in the area remains closed, with stop planks installed at Bridge 211.

Link to comment
Share on other sites

Latest Update

 

Notice Alert

Trent & Mersey Canal

Starts At: Bridge 211, Dutton Hall Bridge

Ends At: Lock 76

Up Stream Winding Hole: Between Bartington Wharf and Bridge 211

Down Stream Winding Hole: Immediately below Dutton Stop Lock (tunnel side of the lock)

Thursday 27 November 2014 15:00 until further notice

Type: Navigation Closure

Reason: Repair

 

Update on 26/02/2015:

 

The repair works at Dutton are now complete and our contractor is away from the site.

However, because of the other works that are on-going to repair wash walls in the area between Preston Brook Tunnel and Soothill Bridge (200) the canal in the area remains closed, with stop planks installed at Bridge 211.

 

What a useless notice CRT - when will it be open?

I note that the other stoppage referred to is due to be completed on 13 March so can we assume that the repaired section will also be open then.

Link to comment
Share on other sites

 

What a useless notice CRT - when will it be open?

I note that the other stoppage referred to is due to be completed on 13 March so can we assume that the repaired section will also be open then.

 

About par for the course with their communication on this job, I'm afraid.

 

Tim

Link to comment
Share on other sites

I called Red Bull this morning to enquire, did get a call back this afternoon, they're hoping to have it open by the end of March but very vague about it.

When I pointed out that it's important for me to know to have any hope of earning any money, he said he'd make more enquiries & call me back on Monday.

 

Tim

Link to comment
Share on other sites

The opening is mentioned in today's boaters update - 13th March.

 

Yes but...

also says "looks like normal traffic will be resuming in plenty of time for Easter", and the most recent stoppage notice says 'Until further notice' - which is what prompted my call.

Right hand, left hand??

 

Tim

Link to comment
Share on other sites

 

Same here!

 

So two of you have had multiple emails confirming 19th March, (from whom?) on the same day as an official stoppage update saying 13th?

 

Odd.

 

Edit as posted same time as SQ's correction.

Why 4 emails?

Edited by Timleech
Link to comment
Share on other sites

 

Edit as posted same time as SQ's correction.

Why 4 emails?

Seem to have got one for each stoppage in the area. On the phone so can't easily post each mail but one is Trent & Mersey Canal

Starts At: Bridge 211, Dutton Hall Bridge

Ends At: Lock 76

Another is Preston Brook tunnel to Bridge 200.

Link to comment
Share on other sites

I emailed David Baldachino Monday to say that it was not clear when the canal would be re-opened. Credit where it is due he responded

very quickly,even though there was a bit of duplication on the notices!

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.
×
×
  • Create New...

Important Information

We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.