CRT very kindly rang me two days ago to let me know about this, don't think its been on here yet:

 

Further to previous advice notices we are now in a position to update customers on the planned closures for the Leeds Flood Alleviation Scheme as follows:

We are pleased to advise that Canal & River Trust customer representatives have been working closely with Leeds City Council and their contractor to look at ways of minimising the disruption from the Leeds Flood Alleviation Scheme.

We can now advise that the previously planned closure of four weeks between 20 February and 16 April for Knostrop Fall Lock is no longer necessary.

Leeds City Council and their contractor have advised that a two week closure 'window' for the removal of the crane from Fearns Island at Crown Point and testing of the weirs at Leeds and Knostrop is required from the 17 July to the 30 July. This is a significant improvement on the original proposal which was 15 February to 19 June.

 

So all good to go up the L&L in April just as I was looking at alternatives.

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.
×
×
  • Create New...

Important Information

We have placed cookies on your device to help make this website better. You can adjust your cookie settings, otherwise we'll assume you're okay to continue.